Costs

Overview of total costs for building this steamlaunch hull.
Prices in Euro, for currency conversion click here

   
Costs made to build hull

Euro

Drawings from Selway Fischer   250
Wood for strongback, buildingjig: 700
machines 1000
handtools 200
Transom and rudder 100
Wood for Planking (red ceddar), stem, hog, bilge runners, clamps (oregon pine) 1900
Wood  for transom and rudder levers 70
Epoxy for glueing strips and laminating 120
more tools 50
more tools 75
several materials 75
More machines 800
More epoxy 500
Wood for outer stem and keel 200
more epoxy stuff 100
Oak for Frames 180
more epoxy 250
Iroko 100
Other 100
SS strips under keel and bilge runner 80
Epoxy and glass sheats for outside 560
Primer and Paint for outside 200
   
   
Total costs to build hull until now 7610
 
   

Hours spend to build hull

h

studying and calculating, 16h 16
Strongback 8 h 8
making malls, 40
setting up moulds, 14h 14
Shopping, 12 h 12
finishing building jig 8
Building transom 8
Transom and transom knee 12
bevelling moulds 10
laminating stem 14
laminating hog 6
glueing hog and stem together 4
correcting stem (cut off wrong part 4
Bevelling hog/stem 2, 6
final bevelling and preparing for strip planking 10
Strip Planking, total hours on avg 2hours per strip 160
Sanding and Priming 16
Outer keel and stem 24
Turning upright and cleaning inside 20
3 layers of epoxt inside Hull 8
Sawing Frames 8
laminating frames 48
cleaning inside 12
coating inside, 2 layers epoxy (white) 10
TOTAL HOURS HULL UPTO NOW 478 = 60 days
   
Inwhale, Inner bilgerunner 16
Floors and engine bearer 40
Propeller shart-log 32
Outer keel and bilge runners 16
Rudder 24
glass sheating 30
SS strips 6
preparing hull for first layer primer 16
   
   
Total building hours  
 